To replace windows in the City of Miami, pick impact products with a current Miami-Dade NOA or Florida approval rated for the 175 mph HVHZ wind speed, get historic or condo approval first if it applies, apply for the permit online through iBuild, pass the inspections, and book a wind mitigation inspection after final.
Last checked: October 24, 2026 · General guidance. Confirm requirements for your address with the Miami building department.
Step zero: is your address inside the City of Miami?
"Miami" on an envelope does not always mean the City of Miami. The city has its own Building Department, and it only issues permits for addresses inside city limits. Neighborhoods like Brickell, Coconut Grove, Little Havana, Edgewater, Wynwood, Allapattah, Flagami, Little Haiti and the Upper Eastside are part of the city.
If your home is in unincorporated Miami-Dade or another town in the county, the permit goes to a different office with its own checklist. Everything below is written for City of Miami addresses.
Why a Miami window job has more rules than most of Florida
The whole City of Miami sits inside the High Velocity Hurricane Zone (HVHZ), which the Florida Building Code defines as Miami-Dade and Broward counties. Inside the HVHZ, windows and doors must pass the county's own test protocols, not only the statewide ones.
Miami-Dade also has the highest design wind speed in the HVHZ. Section 1620.2 of the 2023 code sets 175 mph (3-second gust) for homes in Risk Category II. Broward, next door, is 170 mph. That number feeds the design pressure each new window must be rated for.
These rules trace back to Hurricane Andrew. It made landfall near Homestead Air Force Base before dawn on August 24, 1992, as a Category 5 storm. About 49,000 homes were destroyed and 108,000 damaged. An enhanced South Florida Building Code for Broward and Dade followed in 1994, and the first statewide code in 2002.
- Large-missile test: a 9-pound 2×4 fired at 50 feet per second, two hits per sample, then cyclic pressure loading (FBC Section 1626).
- Small-missile test: 2-gram steel balls, required for units installed more than 30 feet above grade. That covers most condo tower windows.
- Test standards for a Miami-Dade approval: TAS 201, TAS 202 and TAS 203.
Start with your type of home, because the path changes
Miami is mostly a city of large buildings. Census data shows about 43% of its 229,852 homes are in buildings with 50 or more units. Single-family detached houses are only about 21%, and only about one in three homes is owner-occupied. Find your row below before you do anything else.
| Home type | Share of City of Miami homes | What is different |
|---|---|---|
| Single-family house | About 21% | Standard path: product approval, iBuild permit, inspections. Owner-builder permit is an option if you live there. |
| Townhouse / attached | About 9% | Check your association's rules before you choose a product, color or style. |
| Unit in a 50+ unit building | About 43% | Association approval comes first. Units above 30 feet need small-missile ratings. Tall buildings are threshold buildings with extra inspection rules. |
| Home in a historic district | Varies by district | A certificate of appropriateness (COA) is required on top of the building permit. |
The step-by-step process for a City of Miami home
- 1. Measure every opening and note what is there now. Record width and height of each rough opening, the wall type (concrete block or frame), and any mullions between units. Note which windows are in bedrooms. Every sleeping room needs one escape opening with at least 5.7 square feet of clear area (5 at grade floor), 24 inches clear height, 20 inches clear width, and a sill no higher than 44 inches.
- 2. Choose products whose approval covers each opening. Each window and door needs a current Miami-Dade Notice of Acceptance (NOA) or a Florida Building Commission approval. The approval has to cover that opening's size and the design pressure at your address. Expired approvals, or ones outside the current code cycle, are not accepted. Many NOAs also require a permanent Product Control label and approved anchors in concrete block walls.
- 3. Get historic or association approval before you file. If the home is in a historic district, apply for the COA first. If you live in a condo or HOA community, get the association's sign-off on the product and look. Doing this before the order avoids paying for windows the board or the city will not accept.
- 4. Apply for the permit in iBuild. All City of Miami building permits are applied for online through the iBuild portal (apps.miamigov.com/iBuildPortal). Window replacement is not on the city's Easy Permit list, so it goes through regular document review in ProjectDox. Any signed-and-sealed documents must be digitally certified. Miami-Dade's replacement checklist asks for a wall elevation showing each window's size, its approval number and mullion size, plus each NOA; the city posts its own checklists on its Permitting Forms & Documents page.
- 5. Record the Notice of Commencement. Florida law (s. 713.13) requires the owner to record a Notice of Commencement before work starts, unless the job falls under the small-contract exemption in s. 713.02(5).
- 6. Order, then installation day. Materials typically arrive 2–3 weeks after contract for in-stock projects. On install day each old unit comes out, the opening is checked, and the new unit is anchored exactly as its approval says.
- 7. Pass the inspections and close the permit. The City of Miami requires a building inspection for every phase of the work, and inspections are what close the permit. Inspections are scheduled through iBuild. Do not consider the job finished until the permit shows as closed.
- 8. Book a wind mitigation inspection. After final, a wind mitigation inspection on form OIR-B1-1802 can document your new opening protection for your insurer. Have the permit and the product approvals ready for the inspector.
Historic districts: Morningside, Palm Grove and seven more
The City of Miami requires a certificate of appropriateness for any work on a historically designated property. The city names small projects like window replacement directly. The COA is in addition to the building permit, not a substitute.
Minor work gets a Standard COA reviewed by city staff. Larger work needs a Special COA reviewed by the Historic and Environmental Preservation Board (HEPB). Window changes in Morningside, such as switching to horizontal sliders, have gone before that board in the past.
Morningside runs from Biscayne Boulevard to the bay between NE 55th and NE 60th Streets. Palm Grove, designated in 2009, is the city's largest historic district, with homes from 1921 to 1959.
- City of Miami historic districts: Bayside, Beverly Terrace, Buena Vista, Downtown Miami, Lummus Park, MiMo/Biscayne Boulevard, Morningside, Palm Grove and Riverview.
- Plan for the COA review time before you lock in an install date.
Condo and high-rise units in Brickell and along the bay
Brickell is the city's densest neighborhood, a district of condo and apartment towers. Window work there brings three extra layers.
First, units more than 30 feet above grade must pass the small-missile test. Second, buildings over three stories or over 50 feet tall are threshold buildings. Miami-Dade rules call for a threshold inspection by a state-certified Special Inspector, an inspection plan from the design professional, and wind calculations for every opening under FBC Section 1620 and ASCE 7-22.
Third, older towers are on an inspection cycle. Miami-Dade moved building recertification from 40 to 30 years in 2022. Florida's milestone law adds an inspection for condos three or more stories tall at 30 years, then every 10 years. Ask your association whether a recertification or milestone repair plan affects window work in your building.
Older houses and bayfront lots: what to check when you measure
The median Miami home was built in 1984. About 55% of homes predate 1990, and 16% predate 1950, before the post-Andrew code existed. Openings in older houses are often out of square, so measure the rough opening, not the old window. Note any wood buck; buck calculations are required in threshold buildings when the buck is 1-1/2 inches or thicker.
Bayfront neighborhoods take water too. During Irma in 2017, surge reached 3 to 5 feet along Biscayne Bay from Homestead to Brickell, and slightly above 6 feet in spots in Coconut Grove and Brickell. FEMA's preliminary 2024 maps show AE and coastal VE zones along the shoreline. Check the effective flood map for your address before you plan the job.
What changes the quote on a Miami job
This page has no prices. For current Miami price tables, see the Windows Stock Market page at windowsstockmarket.com/impact-window-prices-miami-fl. Before you compare quotes, know what moves the number here.
- HVHZ products only: every opening needs an approval rated for Miami-Dade design pressures.
- Height: units above 30 feet need small-missile ratings, and threshold buildings add inspection and engineering steps.
- Size and count: large openings, sliding doors and the number of door panels drive the total more than small windows.
- Glass and frame choices your association or a historic COA may require.
- Not in a product price: city permit fees, COA review, threshold inspection, Notice of Commencement recording and the wind mitigation inspection. Ask for each to be listed in writing.
Getting help with a Miami project
Vieser Construction is an authorized installer for ESW, Mr. Glass and PGT. We coordinate your complete installation from measurement to final inspection.
Permit assistance is available. Our team coordinates the complete permitting process, including required documentation, engineering and permit submission, when applicable.
Call or text (754) 707-3281 with your City of Miami address, your home type and your opening sizes to start.
Miami window replacement questions
Do I need a permit to replace windows in the City of Miami?
Yes. The City of Miami permit guide says even small jobs like changing windows or doors often need a permit. Window replacement is not on the city's Easy Permit list, so the application goes through iBuild with document review, and inspections must pass before the permit closes.
Can Vieser Construction help with the Miami permit?
Yes. Permit coordination is available for qualifying projects. Our team manages the required documentation, engineering coordination and submission process from start to finish. For City of Miami addresses, the application itself is filed electronically through the city's iBuild portal.
My house is in Morningside or Palm Grove. What extra step do I need?
Both are City of Miami historic districts, so you need a certificate of appropriateness in addition to the building permit. Minor work gets a staff-reviewed Standard COA. Larger changes, such as changing the window style, may need a Special COA from the Historic and Environmental Preservation Board.
Can I replace the windows in my Brickell condo?
Start with your association, since it controls the building's exterior. Units more than 30 feet above grade need products that pass the small-missile test. If the tower is over three stories or 50 feet, it is a threshold building, which adds a Special Inspector, an inspection plan and wind calculations for every opening.
What wind speed do Miami windows have to meet?
The 2023 Florida Building Code sets 175 mph (3-second gust) for homes in Miami-Dade, Risk Category II. That is higher than Broward's 170 mph. Each window's approval must cover the design pressure that wind speed produces at its opening.
Can I pull the window permit myself as a Miami homeowner?
The City of Miami issues owner-builder permits for owner-occupied one- and two-family homes. You must pass an Owner/Builder test given in person at the Building Department in the Miami Riverside Center, 444 SW 2nd Ave. You then take on the permit and inspection responsibilities yourself.
Related
Replacing windows in Miami? We coordinate your complete installation from measurement to final inspection.
Call (754) 707-3281 or request an estimate.
Sources: 2023 Florida Building Code, HVHZ definition, Sections 1620.2 and 1626 (Glass Association / Texas Tech handout) · Florida Division of Emergency Management – Debris Impact Standards · Miami-Dade County Building – Windows, Shutters, Doors and Security Bars · Miami-Dade County NOA document (Product Control Section) · Miami-Dade County – Replace Windows, Mullions or Glass Doors guideline · City of Miami – Apply for or Manage Building Permits (iBuild) · City of Miami – Guide to Getting a Permit · City of Miami – Get an Easy Permit · City of Miami Building FAQs · City of Miami – Repair or Renovate a Historic Property · City of Miami Planning – Historic Districts · City of Miami Historic Preservation – Morningside · Florida Statutes s. 713.02 (Notice of Commencement exemption) · Florida Statutes s. 553.899 (milestone inspections) · Miami-Dade County recertification presentation to the Florida Building Commission (2022) · U.S. Census Bureau ACS 2024 1-year, B25034 Year Structure Built · U.S. Census Bureau ACS 2024 1-year, B25035 Median Year Built · U.S. Census Bureau ACS 2024 1-year, B25024 Units in Structure · Census QuickFacts – Miami city vs Miami-Dade County · National Weather Service Miami – Hurricane Andrew · National Weather Service Miami – Hurricane Irma · FEMA preliminary FIRM panel 12086C0482M (2024) · List of neighborhoods in Miami (Wikipedia) · Brickell (Wikipedia)